Work on the second section of the timber decking now complete. Almost 2000 linear metres of treated local hardwood and over 5000 stainless steel screws. And the whole job completed by one man, Steve Abbott. Great work Steve. Thank you.

The work on the replacement of the main timber jetty is well underway. For the record more than 1920 lineal metres of hardwood timbers are being replaced and the new boards are secured by more than 4000 Stainless bulge batten screws and glue. All the work is hand-done by Steve Abbott. The local hardwood timbers have been treated to ensure long-life.